Goal
Harbor & Vale's legal ops team handles every new vendor contract through one intake process by 15 January 2027, before the annual carrier renewals start.
- Go-live
- 15 Jan 2027
- Signature
- 2 Dec 2026
- Steps done
- 4 of 12
- Open risks
- 3
01Who is involved
Harbor & Vale
- Lucia RomeroLegal ops managerChampion. Runs the pilot and this plan on the buying side.
- Dana WhitfieldVP OperationsBudget owner. Signs the contract.
- Sam KowalskiIT leadTechnical review, single sign-on, data import.
- Joel MbekiLegal counselReviews the contract and data terms.
- Hannah PriceProcurementVendor onboarding and the purchase order.
- Not yet namedSecurity reviewerReviews the security questionnaire. Sam to confirm who.
Quillmark
- Nora LindqvistAccount executiveOwns this plan. First call for any question.
- Ben AchebeSolutions engineerPilot setup, security questionnaire, IT questions.
- Carla RuizImplementation leadKickoff, data import and training through go-live.
- Martin HaleVP SalesPricing approvals, and a sponsor contact for Dana.
02Steps to go-live
| Step | Owner | Due | Status | |
|---|---|---|---|---|
| 1 | Discovery call and agreed success criteria | BothLucia, Nora | 6 Oct | Done |
| 2 | Demo for the legal team | SellerNora | 9 Oct | Done |
| 3 | Technical review with IT | BuyerSam | 13 Oct | Done |
| 4 | Pilot with 20 live contracts | BothLucia, Ben | 27 Oct | Done |
| 5 | Security questionnaire returned | SellerBen | 3 Nov | In progress |
| 6 | Security reviewer named | BuyerSam | 4 Nov | At risk |
| 7 | Pricing and scope sign-off | BuyerDana | 13 Nov | Not started |
| 8 | Vendor onboarding and purchase order | BuyerHannah | 20 Nov | Not started |
| 9 | Legal review of the contract | BuyerJoel | 27 Nov | Not started |
| 10 | Signature | BuyerDana | 2 Dec | Not started |
| 11 | Kickoff, single sign-on and data import | BothSam, Carla | 7 to 17 Dec | Not started |
| 12 | Go-live for legal ops | BothLucia, Carla | 15 Jan | Not started |
Status is one of Done, In progress, Not started or At risk. Dates are agreed with Lucia; any change goes in the change log below.
03Open risks
| Risk | Owner | Effect if it slips | Plan |
|---|---|---|---|
| No security reviewer named yet | Sam | Pricing sign-off moves a week, and every date after it. | Lucia asks the security office on 2 Nov; decide on 4 Nov call. |
| Dana is away 23 to 27 November | Lucia | Signature cannot move later than 2 Dec without missing the import window. | Get pricing sign-off on 13 Nov, before she leaves. |
| IT change freeze from 18 December | Carla | Data import must be finished by 17 Dec, or go-live moves to February. | Import plan agreed at kickoff; test import on 9 Dec. |
04Next meeting
Wednesday 4 November15:00 to 15:30, video call
- Who
- Lucia Romero, Sam Kowalski, Nora Lindqvist, Ben Achebe
- Decision needed
- Who reviews security, and confirm 13 November for Dana's pricing sign-off.
05Change log
- Pilot marked done. Added step 6, security reviewer, at risk. Signature moved from 25 Nov to 2 Dec because Dana is away 23 to 27 Nov.
- Pilot extended from 23 to 27 Oct to include contracts from the Rotterdam office.
- Technical review done. IT asked for the security questionnaire (step 5).
- Plan created after the discovery call and agreed with Lucia.