Quillmark for Harbor & Vale Logistics

Mutual action plan

From pilot to go-live: contract intake at Harbor & Vale

Last updated 30 October 2026 by Nora Lindqvist, after the pilot review call

Goal

Harbor & Vale's legal ops team handles every new vendor contract through one intake process by 15 January 2027, before the annual carrier renewals start.

Go-live
15 Jan 2027
Signature
2 Dec 2026
Steps done
4 of 12
Open risks
3

01Who is involved

Harbor & Vale

  • Lucia RomeroLegal ops managerChampion. Runs the pilot and this plan on the buying side.
  • Dana WhitfieldVP OperationsBudget owner. Signs the contract.
  • Sam KowalskiIT leadTechnical review, single sign-on, data import.
  • Joel MbekiLegal counselReviews the contract and data terms.
  • Hannah PriceProcurementVendor onboarding and the purchase order.
  • Not yet namedSecurity reviewerReviews the security questionnaire. Sam to confirm who.

Quillmark

  • Nora LindqvistAccount executiveOwns this plan. First call for any question.
  • Ben AchebeSolutions engineerPilot setup, security questionnaire, IT questions.
  • Carla RuizImplementation leadKickoff, data import and training through go-live.
  • Martin HaleVP SalesPricing approvals, and a sponsor contact for Dana.

02Steps to go-live

StepOwnerDueStatus
1Discovery call and agreed success criteriaBothLucia, Nora6 OctDone
2Demo for the legal teamSellerNora9 OctDone
3Technical review with ITBuyerSam13 OctDone
4Pilot with 20 live contractsBothLucia, Ben27 OctDone
5Security questionnaire returnedSellerBen3 NovIn progress
6Security reviewer namedBuyerSam4 NovAt risk
7Pricing and scope sign-offBuyerDana13 NovNot started
8Vendor onboarding and purchase orderBuyerHannah20 NovNot started
9Legal review of the contractBuyerJoel27 NovNot started
10SignatureBuyerDana2 DecNot started
11Kickoff, single sign-on and data importBothSam, Carla7 to 17 DecNot started
12Go-live for legal opsBothLucia, Carla15 JanNot started

Status is one of Done, In progress, Not started or At risk. Dates are agreed with Lucia; any change goes in the change log below.

03Open risks

RiskOwnerEffect if it slipsPlan
No security reviewer named yetSamPricing sign-off moves a week, and every date after it.Lucia asks the security office on 2 Nov; decide on 4 Nov call.
Dana is away 23 to 27 NovemberLuciaSignature cannot move later than 2 Dec without missing the import window.Get pricing sign-off on 13 Nov, before she leaves.
IT change freeze from 18 DecemberCarlaData import must be finished by 17 Dec, or go-live moves to February.Import plan agreed at kickoff; test import on 9 Dec.

04Next meeting

Wednesday 4 November15:00 to 15:30, video call
Who
Lucia Romero, Sam Kowalski, Nora Lindqvist, Ben Achebe
Decision needed
Who reviews security, and confirm 13 November for Dana's pricing sign-off.

05Change log